Cost Management
Assignment #2
30% of Final Grade
Chapters 6, 7 & 8
This Assignment has 6 Questions. Answer all questions using Microsoft Word.
Very Important Instructions
How to save and submit your completed assignment:
1.
Put your answers in a separate word document.
2.
Submit the answers only. I.E. Do not resubmit the question.
3.
Submit answers in Micro Soft Word document.
4.
For the true false and multiple choice questions, list in column format, the
number of the question followed by the one best answer. No marks
awarded for explanation or calculations for true and false or the
multiple choice questions.
5.
Completed assignment to be uploaded to the “Assignment #1 Submission”
area posted under Week 5. Ensure that you upload the correct file as
you only have one attempt to upload your assignment. The file
uploaded will be the one that is graded.
6.
Unreadable or unattached files are considered a non submission. Late
assignments will not be accepted.
File Naming:
1.
Assign the file name in the following manner: Student last name, first Name Ass #
2.
Also you must place you full name on the top of the word document
3.
Note: There is a 10% deduction on each submission when these
instructions are not followed.
File Uploading Instructions
1. Open the Submit Assignment 1 icon and upload your
completed assignment.
2.
Use the
Browse button
at the bottom of the page to select
your Word document for uploading
1

Unlock Solution Unlocking…

3.
Click
Upload
Question #1 — ACTIVITY-BASED COSTING (20 marks)
Markham Inc. designs and builds custom windows for luxury homes. Most of the
windows are custom made but occasionally the company does mass production on
order.
Its budgeted manufacturing overhead costs for the year 2006 are as follows:
Overhead Cost Pools
Amount
Purchasing
$
180,000
Production (cutting, milling, finishing)
400,000
Setting up machines
135,000
Inspecting
160,000
Utilities
300,000
Total budget overhead costs
$1,175,000
For the last three years, the company has been charging overhead to products on the
basis of machine hours.
For the year 2006, 100,000 machine hours are budgeted.
Tommy Barry, owner-manager of Markham Inc. recently directed her accountant to
implement the activity-based costing system she has repeatedly proposed. At Tommy’s
request, the accountant and production foreman identify the following cost drivers and
their usage for the previously budgeted overhead cost pools.
Total
Overhead Cost Pools
Activity Cost Drivers
Drivers
Purchasing
Number of orders
500
Production (cutting, milling, finishing)
Direct labour hours
80,000
Setting up machines
Number of setups
1,000
Inspecting
Number of inspections
5,000
Utilities
Square metres occupied
75,000
During this month, the company received an order for 50 window sets from a housing
development contractor. The accountant prepares cost estimates for producing
components for 50 window sets so Tommy can submit a contract price per window set to
the contractor. The following data for the production of 50 window sets is accumulated:
Direct materials
$120,000